Council Update Archive

Kex Gill Update 3rd June 2024

This article is available in audio format, please click on the play icon below to listen.

Work is still progressing well on-site, and we have installed the full 85 metres of steel sheets – known as piles – to create the structural wall required (as shown below).

Work is now underway to reconstruct the carriageway behind the newly installed sheet piles, along with drainage works and the relocation of telephone cables.

We would like to thank you once again for your patience and reiterate that we are doing all we can to complete the repair as quickly and safely as possible.

We still anticipate the road to reopen before the end of June.

Two drop-in sessions will take place in June for you to find out about the work mentioned above, as well as the realignment project. There is no need to book, simply turn up to find out more.

Wednesday 19 June between 6pm and 8pm at Bolton Abbey Village Hall,
Bolton Hall, BD23 6AL

Tuesday 11 June between 6pm and 8pm at St Thomas a Becket Church,
Hampsthwaite, HG3 2HB

Diversion Route
As mentioned previously, road users are being advised to follow the diversion route in place, which is via the A658, A660 and A65 (or by this route reversed). Signage is in place along this route reminding people of the closure and that businesses remain open.

North Yorkshire Council